Technology Blvd. Electric Transmission Project

Benefits

  • Complies with mandatory standards to ensure safety, reliability and to meet future needs
  • Strengthens area reliability
  • Strengthens operational flexibility

Timeline (View Full Timeline)

  • Fall 2024 – Public announcement
  • Fall 2024 – Public Outreach
  • Q1 2025 – File application with the Virginia State Corporation Commission (SCC)
  • Q1 2026 – Anticipated SCC ruling
  • 2025 – 2026 Permitting Finalize engineering, Pre-construction outreach
  • 2027 – Construction

Contact Us

Call us M - F, 8am - 5pm

(888) 291-0190

Impacts

Service Interruption

Your electric service is not expected to be impacted by this project.  