  • New structures located in the same general location as existing structures
  • Complies with mandatory standards to ensure safety, reliability and to meet future needs
  • Minimizes impact to the environment
  • Replaces aging infrastructure

Timeline (View Full Timeline)

Project Schedule (subject to change, pending progress and weather):

  • Late September/Early October 2024, Greenwich-Thalia - Begin preconstruction activities, including preparing access, clearing the right of way, and staking new structure locations
  • October 2024–December 2024, Greenwich-Thalia - Construction activities, including installing fiber between our Greenwich and Thalia substations, and partially rebuilding the transmission line between our Greenwich and Thalia substations
  • November 2024, Lynnhaven-Thalia - Begin preconstruction activities, including access, staking structures, and forestry
  • January 2025–May 2025, Lynnhaven-Thalia - Construction activities, including installing fiber and rebuilding the transmission line between our Thalia and Lynnhaven substations
  • January 2025–June 2025 - Right of way restoration between Greenwich and Thalia substations
  • June 2025–November 2025 - Right of way restoration between Lynnhaven and Thalia substations