Skip to Content

Choose Your State of Service

In order to serve you better, please select your Dominion Energy location services.

Choose Your State of Service

In order to serve you better, please select your Dominion Energy location services.

Select my State

Show Dominion.com Menu
Explore Dominion Energy's Construction Processes Using This Interactive Guide

Benefits

  • New structures located in the same general location as existing structures
  • Complies with mandatory standards to ensure safety, reliability and to meet future needs
  • Minimizes impact to the environment
  • Replaces aging infrastructure

Timeline (View Full Timeline)

    Project Schedule (subject to change, pending progress and weather):
  • July 2024: Greenwich - Thalia: Begin preconstruction activities, including preparing access, clearing the right of way, and staking new structure locations
  • August 2024 - December 2024: Greenwich - Thalia: Construction activities, including installing fiber between our Greenwich and Thalia substations, and partially rebuilding the transmission line between our Greenwich and Thalia substations
  • November 2024: Lynnhaven to Thalia: Begin preconstruction activities, including access, staking structures, and forestry
  • January 2025 - May 2025: Lynnhaven - Thalia: Construction activities, including installing fiber and rebuilding the transmission line between our Thalia and Lynnhaven substations
  • January 2025 - June 2025: Right of way restoration between Greenwich - Thalia substations
  • June 2025 - November 2025: Right of way restoration between Lynnhaven - Thalia substations

Interactive Portal

Related Links

caret
More Links