230 kV Electric Transmission Line and Substation Project

Powerlines Landscape

GeoVoice

Region Map Preview

Explore GeoVoice, an interactive mapping tool. You can:

  • Search for your address
  • Explore approved project routes and structure locations

For tips and tricks on how to use GeoVoice, view the GeoVoice Fact Sheet.

*Please note – this viewer shows multiple Mecklenburg-area projects. To view the approved South Hill project information, be sure to select South Hill in the legend.

*Updated May 2024

Project Construction

Construction on the South Hill Electric Transmission Line Project is split into four primary phases, identified by the line segments below. Some phases of construction may happen concurrently.

  • Phase 1: Unity Substation to county line
  • Phase 2: County line to Tunstall Substation
  • Phase 3: Tunstall Substation to Evans Creek Substation
  • Phase 4: Tap near Taylors Creek to Raines Substation
4 Phase Map Preview

Pre-construction community meetings have been held for Phases 1-3, and access maps shared at those meetings are available below. Please visit our construction overview portal to learn more about our typical construction process.

Benefits

  • Will comply with mandatory standards to ensure safety, reliability and to meet future needs
  • Will provide secure and reliable service to not only the customer substation site, but the broader area as well

Timeline (View Full Timeline)

  • April 2022 – Notify public of the project
  • Summer 2022 – Hosted public community meetings
    • June 1, June 6, June 7, and July 20
  • Oct. 6, 2022 – Submitted application with the Virginia State Corporation Commission (SCC)
  • June 14, 2023 - SCC issued final order. Visit our legal page.
  • Early 2024 – Begin construction
  • End of 2025 – Target project completion

Contact Us

Call us M - F, 8 a.m. - 5 p.m.

888-291-0190
Documents

Construction Related Impacts

Service Interruption

Your electric service is not expected to be impacted.

Traffic

This project is not expected to impact traffic.

Environment

This project may have limited environmental impacts.

Neighborhood

Access to surrounding neighborhoods may be impacted.