  • Maintains current right of way
  • New structures located in the same general location as existing structures
  • Complies with mandatory standards to ensure safety, reliability and to meet future needs
  • Minimizes impact to the community and environment
  • Replaces aging infrastructure

Timeline (View Full Timeline)

  • Summer – Fall 2022: Surveying activities
  • Spring 2023: Danger Tree Surveying
  • Summer 2023: Preconstruction activities: right of way vegetation management and preparing construction access
  • Construction scheduled to occur in two phases:
    • September – December 2023: Phase 1 from Hathaway to Nash
    • March – June 2024: Phase 2 from Nash to Duke Energy Progress connection point in Rocky Mount, North Carolina

Construction-Related Impacts

Service Interruption

There are no planned service interruptions for this project

Traffic

There may be some traffic delays.

Neighborhood

Access to surrounding neighborhoods will not be impacted.