Spring 2025
Phase 5 Tarboro
late 2024 - spring 2025
Phase 4 Bethel-Carolina to Parmele
Aug - Nov 2024
Phase 3 Conetoe to Bethel-Carolina
Mar - Aug 2024
Phase 2 Shiloh to Conetoe
Jan - Mar 2024
Phase 1 Tarboro to Shiloh
Fall 2023
Preconstruction activities, including right-of-way vegetation management and forestry surveying, begin. Later this year, we will install access roads and lay wooden mats to safely reach structures.
Summer 2022
Right of way surveying
Spring 2022
Permitting