The Virginia State Corporation Commission (SCC) is responsible for verifying the need, approving the route and structures and reviewing the environmental impact of certain transmission lines in Virginia.

On 2/9/24, Dominion Energy filed its application with the SCC. The SCC issued its Final Order approving the project on 10/28/24. Documents related to the case are available to the public on the SCC Docket of the SCC website or search by Case No. PUR-2024-000021 in the " Search Cases " section. In addition, interested parties may visit the SCC Case Comments Page where individual mailboxes are available for each case accepting public comments.

Final approval document

To learn more about this process, view our SCC process map  .

SCC Timeline
Updated as of January 24, 2025

April 10, 2024– Newspaper, Landowner, and Gov’t Official Notice
April 24, 2024– Proof of Notice and Publication
May 22, 2024– Notices of Participation deadline
June 26, 2024– Respondent Testimony deadline
July 21, 2024– Staff Report deadline
August 14, 2024– DEV Rebuttal deadline
August 28, 2024– Deadline for interested party comments
September 4, 2024– Deadline for witnesses to notify of desire to testify
September 11, 2024, 10:00AM– Public witness telephonic hearing
September 11, 2024, 10:00 AM– Evidentiary hearing
October 28, 2024– SCC issues final order approving project