Skip to Content

Choose Your State of Service

In order to serve you better, please select your Dominion Energy location services.

Choose Your State of Service

In order to serve you better, please select your Dominion Energy location services.

Select my State

Show Dominion.com Menu

The Virginia State Corporation Commission (SCC) is responsible for verifying the need, approving the route and structures and reviewing the environmental impact of certain transmission lines in Virginia.

On 2/9/24, Dominion Energy filed its application with the SCC. Documents related to the case are available to the public on the SCC Docket of the SCC website or search by Case No. PUR-2024-00021 in the " Search Cases " section. In addition, interested parties may visit the SCC Case Comments Page where individual mailboxes are available for each case accepting public comments. Please note, the mailbox may not be available until a scheduling order is issued, typically several weeks after an application is filed.

To learn more about this process, view our SCC process map .

SCC Timeline
Updated as of March 15, 2023

April 10, 2024– Newspaper, Landowner, and Gov’t Official Notice
April 24, 2024– Proof of Notice and Publication
May 22, 2024– Notices of Participation deadline
June 26, 2024– Respondent Testimony deadline
July 21, 2024– Staff Report deadline
August 14, 2024– DEV Rebuttal deadline
August 28, 2024– Deadline for interested party comments
September 4, 2024– Deadline for witnesses to notify of desire to testify
September 11, 2024, 10:00AM– Public witness telephonic hearing
September 11, 2024, 10:00 AM– Evidentiary hearing

Related Links

caret
More Links