Fall 2025
DTC Substation projected to be complete
Early 2025
Transmission line projected to be in service
December 2024
Transmission line projected to be in service
Late Summer 2023
Begin construction on substation and transmission line
January 2023
DTC Substation Forestry Activities Begin
2022
Permitting and Real Estate
December
Project filed with the SCC
November 18th
Virtual Community Meeting
May - November
Outreach to the community