Spring 2022
Complete right of way restoration
October - December
Replace existing conductor wire
July
Begin access installation and forestry work
May
Hold virtual preconstruction meeting with community
Q3 2020–Q2 2021
Project planning and permitting activities
July
Project announcement sent to landowners along the project corridor