Upcoming
December 2025
Target completion date
2023
April 2023
Construction activity begins
2021
June 24, 2021
SCC issued final order, approving the project
April 1st
Evidentiary Hearing TBD
Q2
Requested date for SCC approval
March 31st
A local public hearing will convene by telephone at 10 a.m., with no witness present in the Commission courtroom.; The Commission will telephone each witness sequentially who has signed up to provide comment
March 26th
Public Comments deadline
March 2nd
Dominion Energy Virginia Rebuttal due
February 19th
Staff Report due
2020
By October 1st
File application with Virginia State Corporation Commission (SCC)
Early September
Virtual community meeting; Community outreach continues
July - August
Meet with local elected officials; Project website launched; Dedicated email/phone open; Solicit input from cultural advocacy groups

Related Links