Late 2025
Project complete (expected)
Summer 2024
Phase I (Valley Substation-West Staunton Substation) construction complete (expected)
Early 2024
Phase II (West Staunton Substation-Staunton Substation) construction began
Summer 2023
Phase I (Valley Substation-West Staunton Substation) construction began
May 2023
Hosted in-person pre-construction community open house
Fall 2022–Spring 2023
Completed pre-construction activities
August
SCC issued Final Order approving project
November
Submitted SCC application
September
Held virtual community meeting
View recording of September 2021 meeting
View recording of September 2021 meeting
Q2 2021–Q2 2023
Permitting activities, coordination with stakeholders, and conceptual design
April
Project announcement sent to community