  • June 2019 - Project announcement postcard sent to neighbors
  • Q4 2019 - Completed soil borings
  • Q3 and Q4 2020 - Begin access, road building, and forestry activity
  • Oct. 2020 - May 2021 - Phase 1 construction from Staunton to Verona
  • April 2021 - Oct. 2021 - Phase 2 construction from Verona to Weyers Cave
  • Oct. 2021 - March 2022 - Phase 3 construction from Weyers Cave to North River
  • Jan. 2022 - May 2022 - Phase 4 construction from North River to Peach Grove
  • April 2022 - July 2022 - Phase 5 construction from Peach Grove to Harrisonburg
  • End of 2022 - Complete final rehab