January 20th
ACOE held a virtual public meeting as part of the NEPA EIS process
March 1st
The D.C. Circuit Court remanded the Army Corps of Engineers permit for the Skiffes Creek transmission line and ordered the Corps to conduct an environmental impact statement.
February 26th
The Skiffes Creek project was energized, improving reliability of the electric transmission system for customers on the Virginia Peninsula - and allowing for the retirement of two coal-fired units at Yorktown.