Fall 2021
Target Completion Date
Summer 2021
Removal of overhead line
September 19th
Construction informational meeting from 5-7 p.m. at the Pilot House Inn Restaurant, Topping, VA.
Fall 2019
August 30th
Received final necessary permits to begin construction. A construction informational meeting will be held prior to construction commencing.
August 21st
Dominion Energy hosted a construction informational meeting for Rappahannock Transition Station. The site plan for the station was approved by the Lancaster County Board of Supervisors.
July 31st
Dominion Energy hosted a construction informational meeting for Greys Point Transition Station. The site plan for the station was approved by the Middlesex County Planning Commissioners Aug. 9, 2018.
December 21st
the Virginia State Corporation Commission issued its Final Order approving the project. The Commission found, among other things, that there is a need for the project and the rebuild will replace the transmission line currently attached to the Norris Bridge with an underground transmission line.
July
Newly produced photo renderings displayed at the White Stone Town Hall.
February 29th
Submitted application to the Virginia State Corporation Commission.
February 22nd - week of March 7th
115kV overhead line design photo renderings displayed at White Stone Town Hall
February 17th
Informational Open House, The Freeshade Community Center, Topping
February 11th
Informational Open House, Mount Vernon Baptist Church, White Stone
Fall
Began preliminary construction activities - However, construction-related activities are on hold pending review and approval through the SCC process
August 20th
Received Army Corps of Engineers permit approval
July 28th
Received VMRC permit approval
Spring
Public Announcement
Spring
Submit permit applications to the Virginia Marine Resources Commission (VMRC) and the Army Corps of Engineers (ACOE)
Fall
Initial Engagement with Middlesex and Lancaster counties regarding project details