Late 2028
Construction complete, restoration begins
2025
Construction to begin
2025
Permitting, finalize engineering, pre-construction outreach
Spring 2025
Anticipated SCC ruling
October 11, 2024
Filed application with the SCC.
Please see Legal Page for more information.
Please see Legal Page for more information.
Late summer 2024
File conditional Use Permit with Chesterfield County for the proposed Orchard Switching Station.
Early Summer 2024
Project announcement
Summer 2024
Community engagement