Skip to Content

Choose Your State of Service

In order to serve you better, please select your Dominion Energy location services.

Choose Your State of Service

In order to serve you better, please select your Dominion Energy location services.

Select my State

Show Dominion.com Menu
Upcoming
Late 2028
Construction complete, restoration begins
2025
Construction to begin
2025
Permitting, finalize engineering, pre-construction outreach
Spring 2025
Anticipated SCC ruling
2024
October 11, 2024
Filed application with the SCC.
Please see Legal Page for more information.
Late summer 2024
File conditional Use Permit with Chesterfield County for the proposed Orchard Switching Station.
Early Summer 2024
Project announcement
Summer 2024
Community engagement
caret
More Links