Upcoming
Late 2028
Construction complete, restoration begins
2025
Construction to begin
2025
Permitting, finalize engineering, pre-construction outreach
Spring 2025
Anticipated SCC ruling
Late summer 2024
File application with the Virginia State Corporation Commission (SCC) and file Conditional Use Permit with Chesterfield County for the proposed Orchard Switching Station
Early Summer 2024
Project announcement
Summer 2024
Community engagement