Spring 2025
Restoration
December 2024
Project Completion
August 2024
Construction
July 2024
Temporary access road construction
November - December 2023
Reconductor short segments of the line near Walney Substation and Sully Historic Site.
March 2024
Begin energized conductor work
November 2024
Construction continuing between Johnson DP and Bull Run
July 2022
Wire Pull: Crews are schedule to pull electric transmission conductor and shield wires across I-66.
June 2022
Wire Pull: Crews are scheduled to remove electric transmission conductor across Lee Highway (Hwy 29) in Centerville, Virginia.
April 2022
Wire Pull: Crews pulled electric transmission conductors and shield wires across Lee Highway in Centreville, VA.
January 2022
Phase 2 construction begins
August 2021
Wire Pull: Crews pulled electric transmission conductor to new structures located outside of Bull Run substation.
Mid-June 2021
Access work begins
June 8th
Access letter sent to neighbors
June 2nd
Received SCC final order
April 22nd
Evidentiary Hearing, 10:00 am VA SCC, Richmond, VA
April 15th
Public Comments deadline
March 20th
Dominion Energy Virginia Rebuttal due
February 28th
Staff Report due
January 29th
Local Public Hearing, 2:00 pm and 7:00 pm at Sully District Government Center, Chantilly, VA
November 1st
Landowner, Gov't Official and Public Notice
To Be Determined
Procedural order issued; public hearing scheduled
August
File application with Virginia SCC
July 9th and 16th
Host two public open houses
May, June 2019
Meet with local elected officials; Project website launched; dedicated email/phone open; and Solicit input from cultural advocacy groups