The Virginia State Corporation Commission (SCC) has regulatory authority over all energy providers in Virginia and requires certification for all transmission lines out of the ordinary course of doing business. or are at or above 138 kV. Among other responsibilities, the SCC validates the need for a proposed line and approves the route and structures. In reviewing a proposed project, the SCC must consider whether potential impacts on scenic assets, historic districts and the environment have been reasonably minimized.

Application Documents - 2020

Application Documents - 2018

Procedural Schedule

The following key dates and developments are related to the SCC review timeline. For the most up-to-date and full listing of motions, rulings and other related documents, please refer to the SCC docket for this case.

  • Aug. 8, 2018 - SCC issues procedural order
  • Sept. 7, 2018 -Dominion Energy issues public notice
  • Sept. 28, 2018 - Dominion Energy files proof of notice and service
  • Oct. 16, 2018 - Notices of participation due
  • Nov. 13, 2018 - Respondent testimony due
  • Dec. 7, 2018 - Staff Report due
  • Dec. 18, 2018 - Dominion Energy rebuttal due
  • Jan. 8, 2019 - Public comments due
  • Jan. 15, 2019 - Public evidentiary hearing (10 a.m. at SCC’s Tyler Building at 1300 East Main Street, Richmond, Virginia 23219)