Mid-Year 2026
Target project completion
Early 2025
Tentative construction start date
January 16, 2024
Final Order (PDF) authorizing Dominion Energy to proceed with this project
View Final Order
View Final Order
Summer 2023
Submit application for approval with the Virginia State Corporation Commission (SCC)
Q1 and Q2 2023
At least two public meetings - February 15, February 16, April 6.
Visit our meetings page for these events.
Visit our meetings page for these events.
Early 2023
Project announcement