2022
2022
Project need date
2020
March
Obtained construction general permits for trenching and horizontal directional drilling (HDD) sections
2018
September 5th
SCC Final Order of approval issued
June 12th
Evidentiary Hearing will begin at 10:00 am
May 8th
Public Evidentiary Hearing, 10:00 am, SCC, Richmond, VA - receiving public witnesses
May 1st
Public Comments - Extended to June 1, 2018
April 12th
Dominion Energy Rebuttal due - Extended to May 11, 2018
March 27th
SCC Staff Report due - Extended to April 27, 2018
February 26th
Local Public Hearing – Shrevewood Elementary School, Falls Church, VA, 7:00 pm
February 9th
Notices of Participation
January 26th
Landowner, Gov’t Official and Public Notice
2017
November 8th
File application with the VA State Corporation Commission
October 5th
Focus Group #3
September 26th & 28th
Open Houses
August 24th
Focus Group #2
July 27th
Focus Group #1
Spring 2017
Outreach to local legislators