Skip to Content

Choose Your State of Service

In order to serve you better, please select your Dominion Energy location services.

Choose Your State of Service

In order to serve you better, please select your Dominion Energy location services.

Select my State

Show Dominion.com Menu
2024
March 2024
Planned outages and weather delays impact project schedule. Transmission work is still on schedule to be completed by December 31, 2026, as ordered by the SCC. Erecting the security wall and installing landscaping may extend into 2027.
2021
June 10th
Telephone hearing for public witnesses on the new construction schedule begins at 7 p.m.
May 14th
Letters mailed to property owners within .25 miles of the substation to inform them of the Hearing Examiner ruling and provide a copy of the Supplemental Information Report. April 30, 2021- The Hearing Examiner issued a ruling.
February 11th
New construction schedule for the project submitted in a Motion for a New In-Service Date filed with the Virginia State Corporation Commission (SCC)
2020
December
Received 38 kV GIS building permit, the last permit needed to finalize the construction schedule.
August
Final design renderings for the future substation wall are available.
View Here.
March 17th
Community Informational Meeting CANCELLED due to coronavirus.
2019
April 11th
Informational meeting to discuss upcoming transformer work and overall project status.
View Presentation.
2017
September 12th
Fairfax County Board of Supervisors voted unanimously to approve Special Exception Amendment
September 8th
SCC issues final order
2016
December
Special Exception Amendment submitted to Fairfax County
Spring
Community outreach and notification of transmission construction start
2014
Fall
Submit application for local approval to construct
2013
Summer
Public outreach, letters, website, community meeting
June
Outreach to state and local officials

Related Links

caret
More Links