June 2025 - November 2025
Right of way restoration between Lynnhaven - Thalia substations
January 2025 - June 2025
Right of way restoration between Greenwich - Thalia substations
January 2025 - May 2025
Lynnhaven - Thalia: Construction activities, including installing fiber and rebuilding the transmission line between our Thalia and Lynnhaven substations
November 2024
Lynnhaven to Thalia: Begin preconstruction activities, including access, staking structures, and forestry
October 2024 - December 2024
Greenwich - Thalia: Construction activities, including installing fiber between our Greenwich and Thalia substations, and partially rebuilding the transmission line between our Greenwich and Thalia substations
(please see project map for rebuild section)
(please see project map for rebuild section)
Late September/Early October 2024
Greenwich - Thalia: Begin preconstruction activities, including preparing access, clearing the right of way, and staking new structure locations