Upcoming
Summer 2026
Projected energization of new transmission line and Germanna Substation
Fall 2025
Real Estate and Survey processes ongoing
Summer 2025
Substation Construction begins
Winter 2025
ROW clearing and T line construction to begin
2024
August 2024
SCC Final order approval received
2023
November 20, 2023
Filed application with the Virginia State Corporation Commission
October 17, 2023
Public community meeting
Late Summer 2023
Public engagement commences and project mailers sent