Upcoming
October 2027
Edsall Project Energized
Q2 2026–Q4 2026
Transmission line construction
Q2 2026–Q4 2027
Substation construction
Q2 2025–Q4 2026
Permitting
2024
May 2024
File the application with the State Corporation Commission
March 2024
Meet with local elected officials
April 2024
Host a public open house
February 2024
Project website launched