Fall 2028–Spring 2029
Right of way restoration activities
Spring 2026–Fall 2027
Construction phase 1 – 230 kV rebuild between Earleys and Tunis substations
March 2026
Prepare construction access
January 2026
Begin forestry activities
Early 2025
Right of way encroachment review
Fall 2027–Summer 2028
Construction phase 2 – 230 kV and 115 kV rebuild between Tunis and Suffolk
Late Summer 2028
Expected rebuild completion
June 11, 2024
SCC issues its Final Order approving the project
Final Order
Final Order
November 2023
File project with the Virginia State Corporation Commission (SCC) for a Certificate of Public Convenience and Necessity (CPCN)
September 12 & 13, 2023
Project Open Houses
Spring 2023
Project announced; public engagement begins