Upcoming
End of 2025
Target Completion Date
2021
October
Phase 2 complete, Phase 3 begins.
What to expect during phase 3.
September 2021
Phase 1 complete, Phase 2 begins.
July
Final approvals to begin construction received. Phase 1 work underway.
What to expect during phase 1.
Summer
Final permits received, construction began
May
Construction activity to begin, pending receiving final approvals
March 17
Community Meeting Video
March 17, 2021 meeting video
2020
November 14
County Board meeting
October 28
Project Update Video
October 28, 2020 meeting video
September 8
Submit Special Use Permit Application for November County Board hearing
August 13
Virtual Community Meeting
August 13, 2020 meeting video
August–September
Solicit written feedback from community through Dominion Energy and Arlington County project websites
July 6
Submit rezoning application
July–September
Outreach