Summer 2028
Complete restoration
End of 2027
Complete construction
Summer 2026
Begin construction
Spring 2026
Hold construction informational meeting
November 2022
Updated project schedule: shifted construction start from 2023 to 2026
November 2021
Announced project to public
Spring 2021 - Summer 2026
Project preparations, including permitting activities, surveying and design, and stakeholder outreach