Through December 2023
Restoration activities (vegetation management) continues through December 2023
March - May 2023
Phase 3 – Cochran Mill to Belmont substations (no W&OD Trail Impacts)
January - May 2023
Phase 2 – Ashburn to Cochran Mill substations (W&OD Trail from Claiborne Parkway to Battlefield Parkway at Tuscarora Creek Park)
August - December 2022
Phase 1 – Beaumeade to Ashburn substations (W&OD Trail from east of Smith Switch Road to Claiborne Parkway)
February 8, 2022
Virginia State Corporation Commission issues a permit to begin construction
May 20, 2021
Project filed with the State Corporation Commission
May 6, 2021
Informational Virtual Community Meeting planned
January - May 2021
Outreach to the community