2023
Phase 2: March – May 2023 (W&OD Trail impacts)
Install two replacement structures along the W&OD Trail near our Beaumeade Substation
Phase 2: March – May 2023 (W&OD Trail impacts)
Finish reconductor between our Beaumeade and Buttermilk substations
Phase 2: March – May 2023 (W&OD Trail impacts)
Reconductor between our Beaumeade and Paragon Park substations, which is along the W&OD Trail east of Smith Switch Road to east of Loudoun County Parkway Summer 2023: Restoration activities
Phase 1: Late January – Early March 2023 (no W&OD Trail impacts)
Install two replacement structures near the 1757 Golf Club
Phase 1: Late January – Early March 2023 (no W&OD Trail impacts)
Reconductor between the W&OD Trail and Waxpool Road along the west side of 1757 Golf Club
2022
December 2022 – January 2023
Pre-construction activities, including laying wooden mats for equipment to reach structures and setting replacement structure foundations
Spring 2022
Surveying activities