Through Spring 2026
Phase 2 Restoration
Early 2024 - Spring 2025
Phase 2 Construction From Cushaw to Balcony Falls
Spring 2023 – Summer 2023
Phase 1 Restoration
Fall 2022 - Spring 2023
Access & Danger Tree Work Begins, Phase 1 Construction from Skimmer to Cushaw
March 2022
Preconstruction Community Meeting
June
Project Update
Postcard
Postcard
March
Project Announcement