Consistent with the company's core values, Dominion Energy is intensely focused on environmental protection and public safety as we continue our coal ash removal efforts.
Legislation passed during the 2019 Virginia General Assembly requires Dominion Energy to remove approximately 6.2 million cubic yards of coal ash currently stored in the North Ash Pond at Bremo Power Station within 15 years. The coal ash must be recycled or placed in a lined landfill that meets Federal Coal Combustion Residuals (CCR) and Virginia CCR regulations. In keeping with this statute, Dominion Energy has submitted rezoning and Special Use Permit applications to Fluvanna County with plans to construct and operate a state-of-the-art, lined landfill on Dominion Energy property beside Bremo Power Station.
For more information on groundwater monitoring and data, visit Dominion Energy's CCR Rule Compliance Data and Information page for groundwater monitoring results and closure plans.
For more information about this project, contact us at 833-742-0462 or at BremoCCR@DominionEnergy.com.
April 29, 2021 - Community Update Meeting at Fluvanna County Community Center, 6:00 p.m. - 7:30 p.m.
April 1, 2021 - Rezoning and Special Use Permit Application Submittal to Fluvanna County
May 11, 2021 - Fluvanna County Planning Commission Meeting and Public Hearing. Rezoning and Special Use Permit recommended for approval by Fluvanna County Planning Commission.
June 16, 2021 - Fluvanna County Board of Supervisors Meeting and Public Hearing. Rezoning and Special Use Permit approved by Fluvanna County Board of Supervisors.
Dec. 8, 2021 - Groundwater Evaluation Results Public Meeting at Fluvanna Community Center, 6:00 p.m. - 7:30 p.m.
Full Rezoning and SUP Application – submitted April 1, 2021
Project Fact Sheet – April 1, 2021
Community Meeting Letter – April 16, 2021
Community Meeting Presentation – April 29, 2021
Approved Rezoning and Special Use Permit – June 16, 2021