The Virginia State Corporation Commission (SCC) is responsible for verifying the need, determining the route and reviewing the environmental impact of certain transmission lines in Virginia.

On June 23, 2023, Dominion Energy filed its application with the SCC. Documents related to the case are available to the public on the SCC Docket of the SCC website or search by Case No. PUR-2023-00110 in the “Search Cases” section.  In addition, interested parties may visit the SCC Case Comments Page where individual mailboxes are available for each case accepting public comments. Please note, the mailbox may not be available until a scheduling order is issued, typically several weeks after an application is filed.

To learn more about this process, view our SCC process map.

SCC Timeline

  • August 18, 2023 – DEQ Report Received
  • September 29, 2023 – Proof of Notice and Publication deadline
  • October 6, 2023 – Notices of Participation deadline
  • October 20, 2023 – Respondent Testimony deadline
  • November 3, 2023 – Staff Report deadline
  • November 17, 2023 – Dominion Energy Virginia Rebuttal deadline
  • November 29, 2023 – Deadline for Public Comments
  • November 29, 2023 – Deadline for public witnesses to indicate desire to testify
  • December 6, 2023 – Public Witness Hearing (telephonic), 10:00 a.m.
  • December 6, 2023 – Evidentiary Hearing, 10:00 a.m., 2nd floor courtroom SCC
  • January 17, 2024 – Hearing Examiner's report issued
  • March 25, 2024 - The SCC issued a final order, approving the project. View final order.