Skip to Content

Choose Your State of Service

In order to serve you better, please select your Dominion Energy location services.

Choose Your State of Service

In order to serve you better, please select your Dominion Energy location services.

Select my State

Show Dominion.com Menu

SCC

The Virginia State Corporation Commission (SCC) is responsible for verifying the need, approving the route and structures and reviewing the environmental impact of certain transmission lines in Virginia.

On 11/14/23, Dominion Energy filed its application with the SCC. Documents related to the case are available to the public on the SCC Docket of the SCC website or search by Case No. PUR-2023-00203 in the " Search Cases " section. In addition, interested parties may visit the SCC Case Comments Page where individual mailboxes are available for each case accepting public comments. Please note, the mailbox may not be available until a scheduling order is issued, typically several weeks after an application is filed.

Timeline

  • November 2023 – File project with the Virginia State Corporation Commission (SCC) for a Certificate of Public Convenience and Necessity (CPCN)
  • Fall 2024 – Anticipated SCC Final Order

On November 14, 2023, Dominion Energy filed its application with the SCC. Documents related to the case are available to the public on the SCC Docket of the SCC website or search by Case No. PUR-2023-00203 in the “Search Cases” section. In addition, interested parties may visit the SCC Case Comments Page where individual mailboxes are available for each case accepting public comments. Please note, the mailbox may not be available until a scheduling order is issued, typically several weeks after an application is filed.

Procedural Schedule

Key dates and developments are related to the SCC review timeline. For the most up-to-date and full listing of motions, rulings, and other related documents, please refer to the SCC docket for this case.

  • January 19, 2024 - Proof of Notice and Publication deadline
  • March 26, 2024 - Notices of Participation deadline
  • April 2, 2024 - Deadline for interested party public comments
  • April 9, 2024 - Staff Report deadline
  • April 16, 2024 - Dominion Energy Virginia Rebuttal deadline
caret
More Links